Kemmerer Street Project Expansion

The Kemmerer Streets project will be expanding into Diamondville starting 6/19/19. The milling subcontractor will be milling between Arctic Circle and the intersection of US 30 and US 189 before jumping to the other end of town where bridge work will continue as the milling extends just past the WYDOT shop on US 189. This work should take from Wednesday to Friday this week. Drivers can expect the road surface to be rough after the milling is completed and some loose rocks may be present on the surface.

Starting Monday the 24th LeGrand Johnson Construction will be paving these areas, with an anticipated finish date for the paving operation of the 28th. Both the milling and paving operations will be completed under flagger controlled traffic conditions, so please plan for extra delays in these areas.