Lower Valley Energy (LVE) resumed its planned upgrades in Swift Creek Canyon after receiving federal approval of engineering plans. The Federal Energy Regulatory Commission (FERC) authorized LVE to proceed on November 10, allowing crews to begin the next phase of work at the Swift Creek Hydroelectric Facility on Monday, November 16.
This work will allow LVE to safely lower the Swift Creek reservoir to expose and assess a damaged sluice gate that failed in July. The damaged gate allowed water to escape from the reservoir, significantly reducing its water level.
As river flows decreased, LVE was able to inspect the submerged gate using an underwater camera. The inspection revealed a hole in the gate. Debris subsequently accumulated around the damaged area, restricting water release and allowing the reservoir to refill to a higher elevation, which remained relatively stable through much of the summer.
As seasonal streamflows declined this fall, the reservoir level gradually decreased again.
Since the gate failure, LVE has been working with FERC and other regulatory agencies to develop and obtain approval for a controlled reservoir drawdown. The process included multiple rounds of engineering evaluations and reviews addressing dam safety, environmental protection, and compliance with the facility’s operating license.
Crews are currently preparing the powerhouse facility to temporarily route water through the hydroelectric penstock, the large pipeline that normally delivers water to the turbine. This temporary arrangement will allow LVE to lower the reservoir in a controlled manner until the damaged sluice gate is exposed and can be more thoroughly inspected. Throughout this process, LVE will maintain the required minimum streamflows in Swift Creek through the damaged sluice gate to protect downstream aquatic resources.
Once the gate is exposed, crews will assess the extent of the damage, identify the necessary repairs or replacement components, and work to raise and secure the damaged gate in the open position.
After the gate is secured and the initial assessment is complete, LVE plans to discontinue the temporary flow through the penstock and return the full river flow to its normal path through the sluice gate and downstream creek channel.
Because the gate has remained submerged, LVE has not yet been able to fully determine the extent of the damage or establish a reliable timeline for permanent repairs. The duration of this temporary operating condition, the necessary repairs, and the schedule for returning the hydroelectric generator to service will depend on the inspection findings and any additional regulatory approvals required.
“This has been a complex process that has required significant engineering work and coordination with federal and other regulatory agencies,” said Bear Prairie, CEO of Lower Valley Energy. “Our priority has been to make sure we can safely access the damaged gate while protecting Swift Creek and meeting our environmental and operating requirements. Getting approval to begin this work is an important milestone, but we won’t know the full extent of the repairs until we can expose and inspect the gate.”
Additional updates will be provided as work progresses. In the meantime, the public is encouraged to observe all posted warning signs, barricades and temporary access restrictions, and to exercise caution near Swift Creek as water levels and flows may change during controlled operations. LVE will continue coordinating with regulatory agencies and taking appropriate precautions to protect public safety, the environment, and the integrity of the hydroelectric facility.